NEW QUESTION # 58
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
- A. The item category of the materials is set tnon-stock item.
- B. The material have no material number.
- C. The item category of the materials is set tstock item.
- D. The procurement type in the material master is set to in-house Production.
Answer: B,D
Explanation:
To create purchase requisitions for the materials used in your project, you must ensure that the materials have a procurement type that allows external procurement and a material number that identifies them uniquely. Some of the possible reasons why no purchase requisitions have been created after releasing the project are:
The procurement type in the material master is set to in-house production (E). This means that the material is produced internally and not procured externally from a vendor.
The material has no material number (N). This means that the material is a non-stock item that is not managed in inventory and has no master record. Non-stock items require manual creation of purchase requisitions. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334e6b54ce10000000a174cb4.html?&version=1909.002
NEW QUESTION # 59
What functionality can you perform with activity elements?
- A. Assign work centers and capacities
- B. Schedule WBS elements
- C. Create relationships
- D. Assign material
Answer: C
NEW QUESTION # 60
How can you confirm the working hours of different work centers for a single activity?
- A. Create multiple confirmations for the activity and use the appropriate work center for each confirmation
- B. Assign multiple work centers to the activity
- C. Enter multiple work centers within a single confirmation
- D. Enter direct activity allocation assigning multiple work centers
Answer: A
NEW QUESTION # 61
What are valid procurement types for stock items? Note: There are 3 correct answers to this question
- A. Planned order
- B. Preliminary purchase requisition for WBS element
- C. Third-party order
- D. Reservation for WBS element
- E. Purchase requisition and Reservation for WBS element
Answer: A,C,E
Explanation:
Stock items can be procured using planned orders, third-party orders, or purchase requisitions and reservations for WBS elements. Preliminary purchase requisitions are used for non-stock items and reservations are used for stock items that are already available in the warehouse. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 62
Which of the following statements apply to project versions? Note: There are 2 correct Answers to this question.
- A. Project versions can be created automatically based on user status.
- B. Project versions are mandatory for Milestone Trend Analysis (MTA).
- C. Project versions can be changed.
- D. Manually created project versions always require a project version profile.
Answer: B,C
NEW QUESTION # 63
You want to allocate overhead rates to a WBS element. What must you assign to the WBS element?
- A. Costing sheet
- B. Results analysis key
- C. Investment profile
- D. Settlement rule
Answer: A
NEW QUESTION # 64
Project Structures
You want to enable user fields for customer project. Therefore you create several field keys. What is the benefit of assigning a field key to the project profile?
- A. The field key is the default value for the WBS element and the activities too.
- B. The tab user fields is invisible.
- C. The field key is hard coded in the WBS element.
- D. The field key is the default value only for the WBS element.
Answer: A
Explanation:
The benefit of assigning a field key to the project profile is that the field key is the default value for the WBS elements and the activities too. A field key is an object that defines which user fields are available and mandatory for a project object, such as a project definition, a WBS element, or an activity. A project profile is an object that contains various default values and control parameters for a project. By assigning a field key to a project profile, you can ensure that all WBS elements and activities created under that project profile have the same user fields settings. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/df72bb53707db44ce10000000a174cb4.html
NEW QUESTION # 65
Which planning method can prevent further rescheduling of activities?
- A. Partial confirmation of activities
- B. Capacity levelling
- C. Capacity requirements activation
- D. Workforce planning
Answer: A
Explanation:
Partial confirmation of activities is a planning method that allows you to confirm a part of an activity's duration or work. This prevents further rescheduling of the activity because the confirmed part is fixed and cannot be changed. The remaining part of the activity can still be rescheduled according to the project progress and resource availability. Reference: https://help.sap.com/viewer/0c9a2f8f9c1b4a2e8b3f7d0c9b6e1d8a/2020.000/en-US/4c5f7a3e6b571014e10000000a174cb4.html
NEW QUESTION # 66
Resources
How are capacity requirements determined?
- A. Using the control key of an activity.
- B. Independent of scheduling and according to the capacity planner group.
- C. Using scheduling and distribution key.
- D. Using scheduling and the capacity category.
Answer: C
NEW QUESTION # 67
Which of the following statements apply to project versions? Note: There are 2 correct answers to this question
- A. Project versions can be changed
- B. Project versions can be created automatically based on user status
- C. Manually Created project versions always require a project version profile
- D. Project versions are mandatory for Milestone Trend Analysis (MTA)
Answer: B,D
Explanation:
Project versions are copies of projects that allow you to save snapshots of project data at different points in time. Project versions are mandatory for Milestone Trend Analysis (MTA), which is a tool that allows you to monitor and compare the planned and actual dates of milestones in a project over time. Project versions can be created automatically based on user status, which means that you can define rules that trigger the creation of project versions when certain user statuses are set for project objects. Reference: https://help.sap.com/doc/0f069b2e08b748f1b480d4c8b46c3c49/100/en-US/6a7a9f0a6e421014e10000000a174cb4.html
NEW QUESTION # 68
The various work packages in the project are described as individual______________. Choose the correct answer.
- A. Tasks
- B. Project definitions
- C. WBS elements
- D. Activities
Answer: D
Explanation:
The various work packages in the project are described as individual activities. Activities are the smallest units of a project that can be planned, executed, and controlled. Activities can be assigned to one or more WBS elements in a project. Activities can also be linked to each other by relationships to define the sequence and dependencies of the work packages. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
NEW QUESTION # 69
Material
Your customer uses Progress Tracking for network components and mantains dates of events manually. They need to implement scheduling of events.
What is the requisites for implement scheduling of events?
- A. Scheduling parameters for material scheduling must be set.
- B. Event scenarios must be defined.
- C. Events must be released manually.
- D. Priority of events must be set.
Answer: B
Explanation:
To implement scheduling of events, event scenarios must be defined. Event scenarios are predefined sets of events that describe typical sequences of activities in a project. Events are points in time that mark the start or finish of an activity or a milestone. Event scenarios can be used to schedule events automatically based on their dependencies and priorities. Event scenarios can also be used to track and monitor the progress of events in a project. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/0673b65334e6b54ce10000000a174cb4.html
NEW QUESTION # 70
Project Structures
Which the following statement regarding networks are correct?.
Note : there are 3 correct answers for this question.
- A. You can assign the same work center to more than one activity on the same network.
- B. During scheduling, the system plans the network activities in such a way that the assigned work center are not overloaded in terms of capacity.
- C. Capacity requirements of a network activity are reduced when the activity is confirmed.
- D. If a network activity requires more capacity than available in a work center, the system automatically proposes an alternative work center.
- E. You can assign more than one activity element to a network activity.
Answer: A,C,E
Explanation:
"You can assign more than one activity element to a network activity." According to SAP Help Portal, "Capacity requirements of a network activity are reduced when the activity is confirmed." According to SAP Press4, "You can assign the same work center to more than one activity on the same network." Reference: 4
NEW QUESTION # 71
Resources
Which of the following transactions can you use to post actual cost for external processing.
Note : there are 2 correct answer for this question.
- A. Creating a service entry sheet
- B. Creating a purchase order.
- C. Approval of a service entry sheet
- D. Posting a goods receipt
- E. Approval of a good receipt.
Answer: C,E
Explanation:
The approval of a service entry sheet and the approval of a goods receipt are both transactions that can be used to post actual costs for external processing." Reference: 3
NEW QUESTION # 72
You are using budgeting and active availability control. How can availability control be activated? Note: There are 2 correct answers to this question
- A. Automatic activation with assignment to an investment program
- B. Automatic activation with the first actual posting
- C. Automatic activation with budget assignment
- D. Background activation (CJBV - Activate Availability Control) l
Answer: B,C
Explanation:
Availability control is a function that monitors whether the budget for a project is sufficient for planned and actual costs. Availability control can be activated in different ways depending on the settings in the availability control profile and the tolerance limits. Some of these ways are:
Automatic activation with budget assignment: Availability control is activated when you assign budget to a WBS element or a network activity.
Automatic activation with the first actual posting: Availability control is activated when you post the first actual cost to a WBS element or a network activity. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/79ceb65334
NEW QUESTION # 73
To which object can you assign a factory calendar?
- A. Milestone
- B. Relationship
- C. Material component
- D. Network header
Answer: D
NEW QUESTION # 74
Project structure.
You intent to work with predefined project coding mask to create project definitions. What do you have to consider?
- A. You can use an indicator to determine that only coded project numbers may be used within the project system.
- B. The standard project definition must differ from the definition of the operative project.
- C. You can create project coding mask X... event if there are project numbers beginning with X.
- D. You can use only numbers for a project coding mask definition.
Answer: A
Explanation:
You have to consider that you can use an indicator to determine that only coded project numbers may be used within the project system. A coded project number is a project number that follows a predefined structure defined by a project coding mask. A project coding mask consists of a project coding key and a coding mask that specify the length and format of the project number and the WBS element numbers. You can use an indicator in customizing to restrict the creation of project numbers that do not follow a project coding mask. Reference: https://help.sap.com/docs/SAP_S4HANA_ON-PREMISE/4dd8cb7b1c484b4b93af84d00f60fdb8/df72bb53707db44ce10000000a174cb4.html
NEW QUESTION # 75
Which objects do you have to maintain to enable automatic assignment of material components to the project? Note: There are 2 correct Answers to this question.
- A. Material master
- B. Network activity
- C. WBS element
- D. BOM item
Answer: B,D
NEW QUESTION # 76
......